ATSR conducted a district-wide master plan study with involvement from a 50-member community task force. Design options considered enrollment projections, building capacity, and deferred maintenance. The school board accepted the task force recommendation, which resulted in the passage of a $22.1 million (two-question) bond referendum that includes building improvements at four schools.
Improvements included
- additional classrooms
- renovation
- secure entries
- mechanical system upgrades
- ag/tech shop
- a science lab
- a 700-seat new auditorium
- fine arts center
- added locker rooms